GENERAL INFORMATION

The road network in Côte d'Ivoire consists of 82,000 km, of which approximately 8,505 km are paved, including 400 km of highways.

 

Evolution of the Road Network (2015-2024) 

Types of Roads

2015

2016

2017

2018

2019

2020

2021

2022

2023

2024

National Roads

6253

6296

6296

6296

6548

6959

7252

7252

7361

8105

Highways

247

247

247

247

247

247

247

247

370

400

Dirt Roads

75386

75386

75386

75386

75028

74880

74587

74587

73899

74055

The length of the paved road network increased from 6,500 km in 2015 to 8,505 km in 2024. 

 

STATE OF THE NETWORK 

The condition of the paved road network is as follows: 

  • Good: 52% 
  • Average: 19% 
  • Poor: 25% 
  • Under construction: 6% 

 

Summary of Road Works Completed from 2015 to 2024

 Investments made in major road projects during the period 2015-2024 represent a total length of 4,261 km, including approximately 2,005 km of new works and 2,256 km of rehabilitation works. 

 

Major Road Projects Completed from 2015 to 2024 

No.PROJECT

LENGTH (km)

YEAR OF COMPLETION

REGION
1Development and paving of the Abidjan - Grand-Bassam highway

29

2015

Abidjan/Sud-Comoé
2Strengthening of the Comoé Bridge - Abengourou - Agnibilekrou road

88

2016

Indénié-Djuablin
3Development and paving of the Boundiali-Tengréla-Mali Border road

43

2016

Bagoué
4Strengthening of the Adzopé-Akoupé-Comoé road

79

2017

5Strengthening of the Ferké - Ouangolo road (C2D)

46

2017

Tchologo
6Development and paving of the Korhogo - Karakoro road

15

2017

Poro
7Strengthening of the Aboisso - Noé road (Ghana border)

60

2018

Sud-Comoé
8Strengthening of the Singrobo-Yamoussoukro Highway (lot 3 and more)

44

2018

Bélier/Yamoussoukro
9Strengthening of the N'Zikro - Aboisso road

25

2018

Sud Comoé
10Development and paving of the Adzopé - Yakassé Attobrou road

25

2018

50Paving of the Zuenoula-Vavoua road

69

2024

Marahoué


Résumé des ouvrages d'art réalisés

No.PROJECT

REGION

YEAR OF COMPLETION

1Philippe Grégoire Yacé Bridge (Jacqueville)

Grands-Ponts

2015

2Béoumi Bridge

Gbêkê

2015

3Bassawa Bridge

Hambol

2015

4Gbéleban Bridge

Kabadougou

2015

5Alassane Ouattara Bridge (Bouaflé)

Marahoué

2015

68th and 9th phase bridge at Cocody Angré (Chu d'Angré Bridge)

Abidjan

2016

7Bettié Bridge

Indénié-Djuablin

2017

8Dioulatiédougou Bridge

Kabadougou

2017

9Aboisso Bridge

Sud Comoé

2018

10Noé Bridge

Sud Comoé

2018

50Kélindjan Bridge

Kabadougou

2021

 This translation captures the essence of the original French text, providing a clear overview of the road network and projects in Côte d'Ivoire.

Distribution of the condition of the paved network

 

Good

Average

Poor

Under construction

Distribution of the condition of the paved network (Oct 2021)

35%

30%

15%

20%

Source: AGEROUTE 

 

Good

Average

Poor

Under construction

Distribution of the condition of the paved network (Nov 2024)

52%

17%

25%

6%

Source: AGEROUTE